Part Two of a Two-Part Series
The last three steps of a six-step process for strategizing for improvement in shop operations when it comes to how we maintain molds.
Optimizing Mold Performance And Maintenance Efficiency |
|||
|
LEARNMORE
This is Part II of a multi-part series. Click here to begin with Part I
The first three steps of a six-step process for strategizing for improvement in shop operations when it comes to how we maintain molds Last month (December 2006) we discussed how optimizing mold performance and maintenance efficiency are different, yet work hand in hand to impact the overall profitability of a molding company. We discussed the first three steps (Clean-up and Organize, Stop the Bleeding and Assess the Damage) of a six-step process and typical objectives to overcome. In the article a chart was shown that demonstrates how to assess the damage by tracking all unscheduled stop reasons to determine the most serious or #1 issue (based on tooling and labor or corrective action costs) that shut down production and the total number of these occurrences. It also is important to remember that the corrective action costs do not reflect press downtime and lost production, which could add greatly to the overall cost of the unscheduled mold stop event. Having access to the frequency, conditions and contributing issues surrounding these stops represents the most rudimentary of initial steps to begin improving mold performance. When you acquire the ability to track and target unscheduled downtime events, you then begin the process of moving from a completely reactive culture into a more profitable, proactive one. Data as a Resource Efficient and accurate troubleshooting is dependent upon our understanding of how the many molding variables in conjunction with maintenance practices, impact the mold design features which prevent us from: (a) molding our part to a spec or (b) running the mold efficiently. If there is no clear-cut resolution to eliminate the defect, then the next step is to better control the inconsistencies that exacerbate the design weakness. This is where categorized data earns its money. You simply cannot rely on memory or random journal entries made manually or electronically in which to base decisions. Step 4: Count the Issues It is here where most shops in the early stages of data assessments are truly shocked at the results. Things are never what they seem. Why? It is human nature for people to remember particular maintenance events more vividly and many times, differently than others based on their own interaction with the event. For instance, repair techs easily recall procedures or events that cause physical pain such as skinned knuckles, pinched or cut fingers. Molds or components that are unwieldy or tedious to work on create anxiety that can bias opinions concerning labor hours required to perform simple tasks. Conversely, issues that are readily corrected through a simple procedure or by installing new tooling are easily forgotten, even though the collective dollars put it at the top of the “things to be concerned with” list. After you have accumulated enough mold stop data to create a list of targets, the next step is to figure out what you want to go after. Step 5: Prioritize One thing I find amazing is the number of shops that do not even attempt to develop a production schedule, instead relying on a “shoot from the hip” mentality in terms of projecting sales (i.e., workload). Even a couple of days notice of a potential mold run would give many repair shop managers the ability to more wisely utilize the time they have a mold on a bench, through job scheduling.
In last month’s chart example, Mold Damage was at the top of the list in both frequency (17) and corrective action dollars ($41,555.76). This would make it the likely #1 target for our shop. At this point the Mold Damage occurrences would be sorted by distribution to see exactly what molds were stopped for damage, when, what tooling was involved, etc. to narrow the field down to a manageable goal, which according to our chart, would be the 51895-CN mold. See Chart 1 (sorted by repair costs). This type of report also makes it easy to sort and filter on different column headings looking for information that might be related to several of the mold stops regardless of mold type. Optimizing mold performance and maintenance efficiency should be taken one step at a time in order not to be overwhelmed and to maintain focus. If necessary, all documentation referring to the production run and relevant shop records should be collected and reviewed further for other linking information. In prioritizing secondary targets, I always look for maintenance items that could be eliminated or significantly reduced by simply making repair techs aware that an issue exists, such as the following maintenance issues. These type of issues that involve incorrect installation techniques or oversights cause much heartburn with process. Though maybe not in the top five of occurrences, these issues always get a lot of publicity in the corner office, so that makes them viable targets in my book. Target Maintenance Issues Second 1. Maintenance Mistakes Step 6: Act Changing Cultures |
|||
| MoldMaking Technology Online is a trademark of Gardner Publications, Inc, copyright 2009. MoldMaking Technology and all contents are properties of Gardner Publications, Inc. All Rights Reserved. |